10.4 Contract Termination
- 19 Dec, 2025
- Com 0
10.4 Contract Termination
- Performance: Contract is completed by all parties.
- Infeasibility: Performance is impossible (e.g., death of unique service provider).
- Mutual agreement: Parties agree to cancel (novation if replaced by a new contract).
- Cooling-period rescission: Statutory right to rescind within a certain time after signing.
- Revocation: Cancellation by one party (may not relieve obligations if not justified).
- Abandonment: Parties fail to perform obligations, allowing cancellation.
- Lapse of time: Contract expires on its stated deadline.
- Invalidity: Void contracts terminate automatically; voidable contracts can be cancelled.
- Breach of contract: Failure to perform gives the damaged party the right to:
- Rescission (cancel and restore pre-contract condition)
- Forfeiture (loss of deposit or other interest)
- Suit for damages
- Suit for specific performance (court orders contract completion)
Check-In Question
- Which of these is NOT a valid reason for contract termination?
Show Answer
Correct Answer: Forgetting about the contract